Construction at Aria on the Bay is steaming along. They have reached the 32nd level and are completing 1 floor per week. At this rate, we should see top-off in early January and completion by the end of 2017.
As of now, 72% of the 648 residences are under contract and the developer is offering a 35% deposit structure for new buyers of select apartments. There is still a nice selection of layouts available with prices ranging from $400/square foot for apartments in the podium up to $700/square foot apartments with direct bay views.